city_hall

Official websites use .boston.gov

A .boston.gov website belongs to an official government organization in the City of Boston.

lock

Secure .gov websites use HTTPS

A lock or https:// means you've safely connected to the .gov website. Share sensitive information only on official, secure websites.

Boston.gov Search

Get direct answers to your questions about City of Boston services, programs, and information. While we strive for accuracy by sourcing directly from Boston.gov, our search can occasionally provide unexpected results. You can help us improve by using the feedback buttons below each answer.

Questions? Contact us at digital@boston.gov.

Choose a search type

Cummins Highway Update: October 2025

Cummins timeline

Our goals for construction this month:

Wood/Harvard to Woodhaven
  • Complete sidewalk construction, raised crosswalks, and more between Wood/Harvard and Woodhaven
  • Complete the roundabout at Weybosset/Greenfield
  • Pave bike lane and road, followed by crosswalks, bus stop markings, and other road markings (Woodhaven to Weybosset)
  • Begin installing permanent signage
Woodhaven to Fairway

By mid-October, we plan to shift construction to the section between Woodhaven and Fairway. This will involve removing the median and paving the center lanes

Coming up this month:

October 6, 2025 - October 10, 2025
  • Begin installing raised crosswalks (Wood to Itasca)
  • Begin paving the bike lane (Wood to Itasca)
  • Install curb and sidewalk at the intersection with Itasca 
  • Finish installing curbs between Savannah and Corman
  • Install curb between Favre and Brockton
October 13, 2025 - October 17, 2025
Woodhaven Detour

  • Begin reconstruction of Woodhaven/Cummins intersection.  Detour Plan: Between the hours of 7 am and 3:30 pm, Woodhaven Street will be closed to general traffic (residents and drivers who need to access properties on Woodhaven Street will still be able to enter/exit)
  • Finish installing raised crosswalks (Wood to Itasca)
  • Continue paving the bike lane and  
  • Install new curb and sidewalk at the western corner of the Ridlon Road intersection
  • Finish installing curbs between Richmere and Bismarck 
October 20, 2025 - October, 24, 2025
  • Prepare road for paving at (milling) intersection at Wood/Harvard and side street intersections
  • Pave the road between Wood/Harvard to roundabout at Weybosset/Greenfield
  • Continue paving the bike lane (Wood to Itasca)
  • Install curbs between Bismarck and Woodhaven
  • Install curbs between Brockton and Favre
  • Install permanent signage 
October 27, 2020 - October 31, 2025
  • Pour concrete for remaining driveways and pedestrian ramps
  • Work on signalized intersections
  • Fill in material for planters and green infrastructure 