city_hall

Official websites use .boston.gov

A .boston.gov website belongs to an official government organization in the City of Boston.

lock

Secure .gov websites use HTTPS

A lock or https:// means you've safely connected to the .gov website. Share sensitive information only on official, secure websites.

Boston.gov Search

Get direct answers to your questions about City of Boston services, programs, and information. While we strive for accuracy by sourcing directly from Boston.gov, our search can occasionally provide unexpected results. You can help us improve by using the feedback buttons below each answer.

Questions? Contact us at digital@boston.gov.

Choose a search type

Cummins Highway Construction Updates: February, 2025

February Updates

  • Work Hours: 7 a.m. - 3:30 p.m.
  • Timeline: ongoing
  • Parking Restrictions: Parking will be restricted on Cummins from Woodhaven Street to Wood Ave during all hours.
  • Our contractor (McCourt) will install light pole bases, conduits, and pull boxes from Itasca Street to Harvard Street.
  • Install drainage structures at Ridlon Road and between Kennebec Street and Hebron Street. *Sidewalks will be temporarily closed with pedestrian detours.
  • Continue paving over sidewalks after conduit installation.
  • In late February, our contractor will begin installing light pole bases, conduits, and pull boxes on the southern side of Cummins from Wood Avenue to Ridlon Road.

Summary of Work Completed in 2024

  • Removed the center median from Woodhaven Street to Wood Avenue/Harvard Street and replaced it with a temporary median.
  • Repaved the roadway.
  • Installed drainage structures and electrical conduit from Bismark/Brockton to Rugby/Savannah.
  • Installed new streetlights and removed old streetlights from Woodhaven Street to Ridlon Road/Itasca Street.