city_hall

Official websites use .boston.gov

A .boston.gov website belongs to an official government organization in the City of Boston.

lock

Secure .gov websites use HTTPS

A lock or https:// means you've safely connected to the .gov website. Share sensitive information only on official, secure websites.

Boston.gov Search

Get direct answers to your questions about City of Boston services, programs, and information. While we strive for accuracy by sourcing directly from Boston.gov, our search can occasionally provide unexpected results. You can help us improve by using the feedback buttons below each answer.

Questions? Contact us at digital@boston.gov.

Choose a search type

Cummins Highway Construction Update: May 2025

Planned Work for the Week of 05/12 – 05/16
  • Work hours: 7:00 a.m. - 3:30 p.m.
  • Start signalized intersection work at Wood Ave. and Harvard St.
  • Excavate and backfill bike lane from Wood Ave. towards Tampa St.
  • Begin installing sidewalks from Itasca to Ridlon Rd.
  • Start Bioretention planter excavation from Woodhaven St. to Brockton St


Planned Work for the Week of 05/19 – 05/23
  • Work hours: 7:00 a.m. - 3:30 p.m.
  • Continue signalized intersection work at Wood Ave and Harvard St
  • Begin installing sidewalks Tampa St. towards Harvard St.
  • Excavate and backfill bike lane from Savannah towards Ridlon Rd.
  • Begin installing sidewalks from Greenfield St. to Ridlon Rd.
  • Start Bioretention planter excavation from Woodhaven St. to Corman Rd.


Planned Work for the Week of 05/26 – 05/30
  • Work hours: 7:00 a.m. - 3:30 p.m.
  • Begin installation of signalized intersection at Itasca St.
  • Begin bioretention plantar excavation from Wood Ave. towards Tampa St.
  • Begin installing sidewalks from Livermore St. to Seminole St.
  • Begin installing sidewalks from Rugby Rd. to Harmon St.