city_hall

Official websites use .boston.gov

A .boston.gov website belongs to an official government organization in the City of Boston.

lock

Secure .gov websites use HTTPS

A lock or https:// means you've safely connected to the .gov website. Share sensitive information only on official, secure websites.

Lost Village Transportation Safety Improvements

We are investing in safer, greener, and accessible intersections and sidewalks in the Lost Village neighborhood

Have questions? Contact:

Project Phase

timeline-graphic
timeline-graphic
timeline-graphic
timeline-graphic
timeline-graphic
Pending
Planning
Design
Construction
Complete

Project Information

Location
Lost Village Improvements Charlestown 02129
See all
Expected Year to be Completed
2026
Primary Project Type
Streets

Construction Updates

Construction Updates
  • Complete new curbs and sidewalks on Brighton Street and Caldwell Street.
  • Continue installing new curbs and sidewalks on Parker Street and Hadley Street.

Temporary parking restrictions and traffic patterns may be required during working hours, and are required to be signed at least 48 hours in advance. Please note all construction signage. The construction schedule is subject to change based on weather conditions and other factors.

  • Complete installing new drainage structures and new curbs on Brighton Street and Caldwell Street.
  • Begin demolishing existing sidewalks on Hadley Street and installing new curbs.

Temporary parking restrictions and traffic patterns may be required during working hours, and are required to be signed at least 48 hours in advance. Please note all construction signage. The construction schedule is subject to change based on weather conditions and other factors.

  • Complete reconstructing curb ramps on the southern side of Cambridge Street at the Parker Street intersection.
  • Complete installing new drainage structures on Brighton Street at Cambridge Street, and Hadley Street and Parker Street at Cambridge Street.
  • Complete installing new curb extensions on Brighton Street at Cambridge Street.
  • Begin installing new drainage structures at Brighton Street and Caldwell Street.

Temporary parking restrictions and traffic patterns may be required during working hours, and are required to be signed at least 48 hours in advance. Please note all construction signage. The construction schedule is subject to change based on weather conditions and other factors.

Caldwell Street drainage relocation in progress on May 15, 2026
Caldwell Street drainage infrastructure relocation progress on May 15, 2026

New curb extensions at Brighton Street at Cambridge Street on May 15, 2026
New curb extensions at Brighton Street at Cambridge Street on May 15, 2026
  • Complete sidewalk reconstruction on Medford Street.
  • Continue installing new drainage structures on Brighton Street at Cambridge Street, and Hadley Street and Parker Street at Cambridge Street.

Temporary parking restrictions and traffic patterns may be required during working hours, and are required to be signed at least 48 hours in advance. Please note all construction signage. The construction schedule is subject to change based on weather conditions and other factors.

Medford Street sidewalk reconstruction in progress on May 4, 2026
Medford Street sidewalk reconstruction in progress on May 4, 2026

Brighton Street at Cambridge Street drainage relocation work in progress on May 5, 2026
Brighton Street at Cambridge Street drainage relocation work in progress on May 5, 2026
  • Begin reconstruction on a northern section of sidewalk on Medford Street from Main Street to Shor`t Street, which will include four new street tree pits.  
  • Begin installing new drainage structures on Brighton Street at Cambridge Street, and Hadley Street and Parker Street at Cambridge Street.

Temporary parking restrictions and traffic patterns may be required during working hours, and are required to be signed at least 48 hours in advance. Please note all construction signage. The construction schedule is subject to change based on weather conditions and other factors.

Project Highlights

The City has received mitigation funds from the Massachusetts Gaming Commission which have been allocated to this project. The project will focus on making traffic calming improvements and expanding green infrastructure within the Lost Village in Charlestown by:
 
  • Reconstructing sidewalks, crosswalks, and ramps to be ADA-compliant to make walking and rolling accessible for everyone.
  • Building curb extensions and raised crosswalks at intersections to improve safety by slowing turning vehicles and increasing visibility.
  • Modernizing traffic signal equipment, adding Audible Pedestrian Signal buttons, and updating signal timing at the intersection of Cambridge Street and Parker Street.
  • Install high-visibility striping, and add new signage in the project area. 
  • Incorporate green infrastructure by improving drainage and installing new tree pits planted with native species to support rainwater infiltration, reduce the urban heat island effect, and beautify the neighborhood.

Design Details

Cambridge Street Intersections Design Details

Hadley street including the intersection of parker street and cambridge street

To improve your safety and accessibility we will:

  • Upgrade all curb ramps to be ADA-compliant and rebuild most sidewalks. 
  • Build curb extensions at intersections and widen sidewalks for shorter, more visible crossings.
  • Repave the roadway and refresh all pavements markings for a smoother path of travel.
  • Install 4 new tree pits to reduce the urban heat island effect and beautify the neighborhood.
  • Upgrade and recalibrate signal equipment to improve the experience for all users.
Intersection of brighton street and cambridge street

To improve your safety and accessibility we will:

  • Upgrade all curb ramps to be ADA-compliant and rebuild most sidewalks. 
  • Build curb extensions and a raised crosswalk with daylighting for shorter, more visible crossings.
  • Repave the roadway and refresh all pavements markings for a smoother path of travel.
  • Install 2 new tree pits to reduce the urban heat island effect and beautify the neighborhood.

Caldwell Street and Brighton Street Design Details

Intersection of Caldwell Street and brighton street

To improve your safety and accessibility we will:

  • Upgrade all curb ramps to be ADA-compliant and rebuild sidewalks at the intersection. 
  • Build curb extensions and a raised crosswalk for shorter, more visible crossings.
Back to top