city_hall

Official websites use .boston.gov

A .boston.gov website belongs to an official government organization in the City of Boston.

lock

Secure .gov websites use HTTPS

A lock or https:// means you've safely connected to the .gov website. Share sensitive information only on official, secure websites.

Last updated:

Harrison Avenue Reconstruction (Ink Block)

We’re designing a safer, greener Harrison Avenue between Herald Street and East Berkeley Street.

Our work will continue the public realm improvements started by the redevelopment of parcels along the corridor. This fall, we are finishing design plans and aim to begin construction next year.

TALK WITH US!

Events

DESIGN

The designs for Harrison Avenue have been finalized, please find the link here:

VIew the design plans (PDF)

  • Better sidewalks and safer crossings
    • Rebuild all curb ramps to meet accessibility standards
    • Widen the sidewalk on the west side between Traveler Street and East Berkeley Street
    • Build pedestrian islands at each intersection to shorten crossing distances
    • Install fresh, high visibility crosswalks
    • Use pedestrian-friendly signal phasing at signalized intersections
  • Smoother Road
    • Repave the road between Herald Street and East Berkeley Street, making a more comfortable experience for all users. 
  • Separated bike lanes
    • Add one-way separated bike lanes on both sides of the street, allowing travel in both directions
  • Green and resilient
  • Public realm
    • Install standardized street lighting, replacing non-standard street lights
    • Remove the decaying concrete median
  • Safer, more efficient signals and traffic
    • Where possible, people on foot will get a head start crossing the street before drivers going in the same direction
  • Parking 

Project Map

Harrison Avenue Ink Block - Project Map

Project Updates

Project Updates

On October 1, 2024 we attended the East Berkeley Neighborhood Association Meeting. We presented the finalized plan documents and requested feedback especially around the community's desires for curb uses. We heard about concerns around emergency vehicle access, illegal and uncourteous uses by delivery vehicles, and concerns around pedestrian's desired pathways through the corridor. We are working on an email update to share with the EBNA and encourage you to sign up for our future emails at the subscribe for updates link below. 

October 1 PRESENTATION

On August 6, 2024 we attended the Landmarks Commission hearing to present the current project status and field questions from the commission.

August 6 PRESENTATION

On September 13, 2022 we attended the East Berkeley Neighborhood Association Meeting to share an update and take feedback

September 13 PRESENTATION

On August 9, 2022, we attended the East Berkeley Neighborhood Association Meeting to share an update and take feedback

August 9 PRESENTATION

Back to top