Project Name

Olmsted Green - Mixed Income Rental

This project has been completed and no further work is being done.
Project Parcels

1405198500

Harvard ST
Owner:
Other
299,048sqft
Project Images

6 PHOTOS

Neighborhood
Mattapan
Councilor
Worrell
Units Total
100
Income-Restricted Units
100
Property Size
679,417 sq/ft

Developer

New Boston Fund

Project Goals

This project is located on the former Boston State Mental Hospital site in Mattapan and is part of a multi-phase development to create over 500 units of housing being led by Lena New Boston LLC. The development project includes the creation of creation of 100 mixed-income rental units in 24 townhouse buildings set back from Harvard Street in Mattapan. Keeping the city affordable is one of the City's key goals; the affordability mix of this project will be 16 rental units at or below 30% AMI, 24 rental units at or below 60% AMI, and 60 market-rate rental units. The project was awarded DND funding in 2016 and Massachusetts Department of Housing and Community Development for Low Income Housing Tax Credits in 2017. The project is under construction and slated for completion in 2020.

Timeline

Winter 2016

Funding awarded

Mayor’s Office of Housing approved funding for this project.
Winter 2016

City Planning

This project is going through a zoning review with the Boston Planning and Development Agency (BPDA). Then we’ll work with the Developer on funding, design, and compliance.

Fall 2018

Under Construction

Construction is underway. For further information on road closures and parking impact, contact the Project Manager.

Summer 2020

Project Complete

This project is ready for use.

    Back to top