city_hall

Official websites use .boston.gov

A .boston.gov website belongs to an official government organization in the City of Boston.

lock

Secure .gov websites use HTTPS

A lock or https:// means you've safely connected to the .gov website. Share sensitive information only on official, secure websites.

Social Media Survey
/
We want to better understand where folks in the City of Boston are finding news and information through social media. To help with this effort, please take our quick survey today:
< Go to Building Housing Homepage
Project Name

Building N (250 Centre Street)

Project Parcels

1101197000

50 LAMARTINE ST
Owner:
Other
251,810sqft
Project Images
Neighborhood
Roxbury
Councilor
Weber
Units Total
110
Income-Restricted Units
110
Property Size
364,992 sq/ft

Developer

The Community Builders, Inc.

Project Goals

**If you are interested in applying for an apartment in this building, please visit www.250centre.com to get updates about the project and sign up to receive an application when they are available.**

The Community Builders (TCB) are constructing a new, 110 unit mixed-income rental development along with 1,775 square feet of neighborhood oriented retail space. 76 of the new rental units will be income restricted affordable housing units, while 34 will be unrestricted, market rate rental units.

Building N will be the 5th project to be constructed under the Jackson Square Master Plan, and is located on the same site as Building M, a 44 unit affordable rental housing project being constructed by the Jamaica Plain Neighborhood Development Corporation.

Building N has been awarded funding by the City of Boston Department of Neighborhood Development and the Neighborhood Housing Trust, and was awarded State funding in 2020. Construction began in August 2021.

Timeline

Winter 2017

Funding awarded

Mayor’s Office of Housing approved funding for this project.
Winter 2017

City Planning

This project is going through a zoning review with the Boston Planning and Development Agency (BPDA). Then we’ll work with the Developer on funding, design, and compliance.

Aug 09 2021
Building N at 250 Centre Street is ready to begin construction! All of the lenders to this project finalized their funding as of August 6th, and construction mobilization begins immediately. The construction period for the building is expected to last 18 months.
Joe Backer | Project Manager
Summer 2021

Under Construction

Construction is underway. For further information on road closures and parking impact, contact the Project Manager.

Summer 2023

Project Complete

This project is ready for use.

    Back to top