John J. Ryan Playground Improvements
The second phase of construction is about to begin at Ryan Playground. This part will include installing the berm, a critical new piece of infrastructure to protect the park and Charlestown from sea level rise and storm events. In addition, we will have new ballfields, playground and splash pad, street hockey rink, seating areas, pathway and sports lighting!
Sign up for project updates!Project Phase
Project Information
We are about to begin Phase 2, when we build the actual playground and sports fields. Once the contractor has fully mobilized, we will be posting construction updates below on a monthly basis.
- Project Features: Little league, multi-use field, passive use, playground and water play.
- Budget: Second Phase: $16 million
- Consultant: Weston and Sampson
- Contractor: Fleming Bros. Inc.
Upcoming meetings
Upcoming meetingsVideos
Design Meeting #1 (September 21, 2021)
The project team presented their findings and the community provided input and insight.
Sullivan Square Open Space Meeting (October 12, 2021)
The joint meeting between Parks, BPDA, BTD, and Hood Green discussed the future of open space in the Sullivan Square area.
Design Meeting #2 (December 16, 2021)
The project team presented different design concepts and the community provided feedback.
Design Meeting #3 (March 15, 2022)
Project team presented the final design and the community provided feedback.